The High Cost of Remedial
Repairs on Metal Roofing
....Why?
By Robert Stanford
Originally published in Metal Construction News, January
1988
As a metal roofing consultant
I am often asked why remedial repairs are so costly. Architects, owners,
contractors, surety and construction bonding companies, attorneys, and
even metal roofing manufacturers all get that "deer in the headlight
look" when they realize that repairs are often more costly than
the original construction. How can that be?
One project had an original
metal roof construction cost of $700,000. Remedial repairs cost over
$1,600,000.
A similar project cost
$350,000 for a metal roof system. The owner expects to spend approximately
$1,000,000 for remedial repairs.
A school district paid
$400,000 for a metal roof system. They now expect to spend $700,000
to $900,000 for its replacement.
To say that these situations
generate frustration, disbelief, and even anger is an understatement.
There are at least
six distinct factors that impact and contribute to the cost of remedial
repairs for metal roofing. These factors are as follows:
I
The "Botched Surgery"
Analogy
Imagine that you are a experienced, respected,
and competent surgeon. A patient who has recently had major abdominal
surgery and is not doing well comes to you for consultation and examination.
Upon examination you discover that there are ruptured sutures inside
the patient, resulting in internal bleeding. He also has a fever and
a serious infection. X-rays reveal medical instruments that were left
inside the abdominal cavity during the original surgery (clamps, sponges,
etc.) These are serious, life threatening concerns. You are charged
with the responsibility of making necessary surgical corrections (remedial
repairs) and restoring the patient to good health. Realize that from
most outward appearances this patient will look the same after the completion
of your corrections (remedial repairs) as he did before. There are several
key factors at work in this illustration:
The repairs (removing clamps, sponges,
etc.) make take only a few minutes to complete, but you are going
to have to perform intrusive surgical procedures on the patient to
get to this work. In other words, fixing the problem may be quick,
but getting to the problem may take hours. This is a primary factor
in remedial repairs on metal roofing. The actual repair or material
replacement may take just a few minutes to perform, but it may take
a full day or more to remove materials to get to the damaged area,
and a full day or more to replace and re-install those same materials.
This requirement and concept is often very difficult for persons to
see or appreciate.
At the time of his original surgery,
the patient was healthy and in good condition. Now he is sick. Care
and concern for his state of health are more of an issue now than
at the time of the original surgery. This may require additional medical
staff members, specialists, time, etc.
We can look at necessary remedial repairs
on a metal roof in the same context as the illustration above. Standing
seam metal roofing has a fairly high level of complexity. Building design
factors often make metal roof systems "accessory intensive."
Metal roofing is sequential in its installation methods and procedures.
Many systems are also directional in their method of installation (Start
at one side and end up at the other.) So while the scope of work for
certain remedial repairs may be simply defined, such as: "Remove
the one punctured panel and replace with a new panel," it may require
disengaging and removing substantial portions of the roof, flashings,
and accessories just to get to that damaged panel.
All of this takes time, skill, care,
and attention to accomplish. Those items cost money.
II.
Redundancy
This is sometimes a by-product of the "botched
surgery" analogy as outlined above. It is often necessary to make
repeated or redundant efforts to achieve repairs. An actual case history
of one recently repaired project illustrates this point. Consider the
sequence:
The Problem:
Water infiltration into the building at three places:
- The eave.
- Mid-point at the roof panel lap joints.
- The ridge closure and cap flashing.
The repair method dictated the following
requirements:
- Disengage the metal panels from the
eave line.
- Disengage at least 20 l.f. of the
standing seam from the eave back up the roof.
- Remove structural clips and fasteners
for the entire 20' line of panel disengagement.
- Raise the panels high enough to work
under them at the eave line, about 6".
- Place a support member (2x4, 2x6,
etc.) under the raised panels to hold them in place during the repair
procedure.
- Remove eave cleats, damaged flashings,
fasteners, old sealants, etc.
- Clean all remaining surfaces.
- Install new sealants, flashings, etc.,
as required by the Scope of Work / Outline of Remedial Repairs provided
by the metal roofing consultant.
- Follow manufacturer's installation
instructions and re-install the panels, clips, fasteners, etc.
- Mechanically seam (if required) the
panels, clean all exposed surfaces, prepare work for inspection
and water testing by metal roofing consultant.
- Move on to the next areas of repair
at the panel lap joints, closures and ridge cap.
With minor alterations to the descriptions
and Scope of Work, the additional repairs at panel lap joints, etc.
will require many of the same treatments and methods as described for
the eave repairs.
As can be seen from this outline,
this represents a great deal of work and effort to accomplish what may
appear to be minor repairs. Many redundant and tedious procedures come
into play to complete these repairs. It should be easy to see that the
repair process, as outlined above, can take more time and effort than
the original installation of these materials.
More time and effort equal more cost.
III.
The "Do It Right The
Second Time " Factor
This one is easy and short. Simply stated,
"It usually takes longer to do something right than it does to
do it wrong." Taking longer equals more time and effort. More time
and effort equal more cost.
IV.
New Construction vs. Occupied
Building
New construction scheduling places the
roofing contractor and roofing material on the jobsite after the erection
of structural members and installation of roofing substrates. Usually
the plumbing, electrical, and mechanical rough outs are being built
and installed during this same sequence. The building is "on slab,"
and there are no finishes in place.
Such circumstances allow the roofing contractor
the opportunity for "production labor" in the installation
and completion of his work. Translation: If a rain storm
comes, the roofing crew simply gathers their tools and go home. After
all, any rain that may come into the building is simply going to be
on the slab. There is nothing to damage from water infiltration. The
concrete slab won't wash away.
Obviously, this is not the case with
a completed and occupied building. Now water infiltration goes onto
floors, carpet, walls, ceilings, furniture, phone lines, electrical
conduit, equipment, HVAC controls, computers, materials, and people.
It follows that remedial repairs
become a matter of "weather watching," and rob the contractor
of the opportunity for production. Concerns for making sure that no
leaks occur in the occupied building far outweigh the desire for speedy
installation. The contractor cannot open more roof than he can protect,
cover, or complete in the event of inclement weather. It is not uncommon
to open a specific area for repairs, then be forced to cover, close,
and protect that same area when bad weather approaches, then re-open
the area to continue the repairs after the weather has passed, only
to be forced to repeat the protection process a few hours later when
more inclement weather comes calling.
The contractor may schedule repairs for
a certain portion of the job, engage in the repair work and process,
then be informed by the building occupants that he needs to stop work
in this area for a period of time. The reason may be that noise from
the repairs is being translated into the classroom, store, office, conference
room, exam room, etc., below.
These items and concerns take time. Time
equals money.
V.
Installer / Contractor Skill
Levels
If a building project is in need of remedial
repairs (See # I: "the botched surgery factor") then it follows
that the original installation was improper. Improper design and metal
roofing profile selection are factors that often result in leaks and
failures. Quality minded manufacturers are now requiring that they participate
in the design process and geometry of metal roofing system applications
before they will agree to issue weathertightness warranties. While poor
design and product selection can lead to problems, it is improper installation
that takes the dubious award for being the greatest single problem in
the metal roofing industry. Most likely this holds true for all roofing
systems and materials. Logic leads to the conclusion that the original
contractor either did not posses or did not apply the skills required
to accomplish a quality, weathertight installation. A higher level of
experience and skills are required to remedy the situation. Higher levels
of skill equal higher cost.
VI.
The "Fish Bowl"
Factor
There is a predicable time cycle leading
up to remedial repairs. A common "gestation period" is from
2 to 4 years after original construction completion. Within this time
frame the building owners or occupants have most likely endured repeated
leaks that produce interior damage and maximum frustration. Probably
they have made the phone calls, conducted the tours, attended the meetings,
reviewed the warranties, witnessed attempted repairs, (usually the caulking
gun warriors), and called their attorneys. At this stage, these persons
are not amused, nor do they tend to be light hearted or casual about
the problems they have endured. They are skeptical, wary, and mistrustful
of any promises made by people who are now going to "solve the
problem." In a sense, the contractor charged with the responsibility
of remedial repairs may be sailing into hostile waters.
These conditions and attitudes lead to
the "fish bowl factor" listed above. This means that the building
owners are going to inspect, challenge, observe, question, and pay close
attention to everything that is done. They may be demanding, abrupt,
and even uncooperative with the persons performing the remedial repairs.
"We are watching you" may be their bywords.
The building owners are going to expect
accountability and documentation for all actions and repairs. Building
maintenance persons or other staff members may be assigned to oversee
the repairs. They are probably going to hire or engage the services
of their architect or consultants, and expect daily involvement and
reports from these persons.
Kindness, patience, and outstanding "people
skills" are required to meet these challenges. Persons performing
the repairs are going to be asked to explain what they are doing and
why they are doing it that way. Resolution and customer satisfaction
are not going to be achieved if the contractor is harsh, abrupt, or
irritable with the owner or their representatives.
It takes time to gain the owner's confidence
and provide the comfort level that is needed. Time is part of the definition
of patience. Time equals cost.
Conclusion:
The real key, of course, is to eliminate
the need for remedial repairs. There is simply no substitute for good
design, quality product selection, and proper installation. Building
owners can achieve this goal by engaging the services of a qualified
metal roofing consultant and using those services to achieve the results
listed:
Building design and roof geometry that
is compatible with the desired metal roofing system. Selection of
a metal roofing manufacturer who provides engineering assistance,
along with well tested and well designed metal roofing profiles and
systems.
Plans, specifications, details, contract
documents, shop drawings, and design/installation manuals that assist
qualified contractors to perform proper installation of the metal
roofing system.
The issuance of meaningful, well defined
warranties from quality metal roofing manufacturers.
Everyone benefits from quality. Building
owners are the final customer in the construction business. Whether
they pay one dollar or fifty million dollars, if they do not get the
materials and installation set forth in the contract documents, then
they paid too much. Design professionals and metal roofing consultants
share an obligation and duty to assist, educate, and help all persons
interested in quality.
Back
to "Published Articles"

Robert Stanford
& Associates, Inc.
Metal Roofing Consultants
rsametal@earthlink.net
4106 Waterstone
Drive
Missouri City, TX 77459-1837
Phone: 281.261.8522
Mobile: 713.202.5468
Website written
by Expert
Communications, Inc.
Website designed by
MCG Tec Services